Piers and Footings

Today piers and footings were dug and filled with 25 cubic meters of concrete.  The deepest pier was 2.5m (the front of the block). The guys worked all day, commencing 6am and finishing 6pm. The concrete pump truck left the site when it was dark.  Engineer has been to site to check footings and also met the surveyor.  He will come back at 6am tomorrow morning to check whether everything is at the right place.  He was the one came on site on Tuesday to mark out where they should dig and pour today.   Plumber will do the underground plumbing work tomorrow.

Checked against Engineer report, all matching!



Morning - starting


The whole arm went into the pier whole



Night - Finishing soon