Gyprock, plaster and Stairs
Gyprock started on the 23rd August 17. We came home from work and were surprised that there was lights in the house. Went down had a look around 8:30 at night, two people were still there doing the gyprock work.
Cladding on the West side wall started on the Monday, 28th of August and completed the next day.
Plastering started Wed 30 August
Stairs and glass balustraude went in on the 6 September. They are looking good.
Void over entrance
The brick columns in the front facade were completed on the 6 September. The brick work outside the pantry window was also corrected today.
Cladding on the West side wall started on the Monday, 28th of August and completed the next day.
Plastering started Wed 30 August
Stairs and glass balustraude went in on the 6 September. They are looking good.
Void over entrance
The brick columns in the front facade were completed on the 6 September. The brick work outside the pantry window was also corrected today.
The stairs look great!